Progress Report Week 8.
 
Week 8 has seen the commencement of the timber frame erection.
 
Setting of sole plates.
 
 



Installation of ground floor panels begins.

 
Installation of internal ground floor panels.


 
Installation of acoustic insulation into party walls.

 

 
The scaffolding company also returned to site to complete the scaffold around the bungalow and to fill in the front section of the apartments and complete the second lift.
 
Next week will see the continuation of the timber frame works and more scaffolding.