Progress Report Week 7.
Week 7 has seen the completion of the internal drainage and the substructure for the timber frame to sit on.
Grouting of floor and construction of substructure.
The erection of the scaffolding has begun, ready for the timber frame .
The site has been stoned up ready for the arrival of the timber frame and future works.
The scaffolding of the bungalow will commence next week.
If you haven't already heard we are holding a Community Liaison Open Evening on Thursday 3rd October at Barnabas C of E Church on Westbury Crescent.
It will run from 4-6.30pm, with Q&A time at 5 & 6pm, refreshments provided.
We look forward to seeing you there and answering any questions/ suggestions you may have?