Progress Report Week 6.
Week 6 has seen the return of the ground workers and we have started to backfill around the buildings ready for the installation of the floors.
The installation of the floors on the apartments has begun, this will be followed by the internal drainage and ductwork for services.
The substructure of the lift shaft is complete and the works for the timber frame sole plate have begun.
The drainage and floors are now being installed on the bungalows.