Thursday, 7 November 2013

Progress Update

Progress Report Week 9.
 
Week 9 has seen the continuation of the ground floor timber frame erection along with the commencement of the first floor joists, floor decking and the adaption of the scaffolding ready for the first floor panels.
 
Joists have been installed.
 
 
Laying of the temporary floor deck on the first floor of the apartments.


First floor panel installation has begun.

 
Second floor joist installation is underway.

 
Installation of fire barriers around windows has begun and lapping of membranes is in progress.

 