Progress Report Week 11.
Week 11 has seen the commencement of the flat roof works and the installation of the trusses on the bungalow.
Soft landing bag installation nearly complete, prior to the lifting of the roof trusses.
Trusses on bungalow one are now in position.
Flat roof works have commenced and guess what?
Its raining!
.The trusses on the bungalow have been installed, bracing fitted, hips and valleys formed.
The fire barriers and lapping of the membranes has been completed on the 100mm cavity elevations of the apartments.
After a hectic week everything has been secured down ready for the storm of the year.
Hopefully when we return on Monday the buildings will be where we left them?