Monday, 14 October 2013

Progress Update

Progress Report Week 8.
 
Week 8 has seen the commencement of the timber frame erection.
 
Setting of sole plates.
 
 



Installation of ground floor panels begins.

 
Installation of internal ground floor panels.


 
Installation of acoustic insulation into party walls.

 

 
The scaffolding company also returned to site to complete the scaffold around the bungalow and to fill in the front section of the apartments and complete the second lift.
 
Next week will see the continuation of the timber frame works and more scaffolding.



Tuesday, 1 October 2013

Progress Update

Progress Report Week 7.
 
Week 7 has seen the completion of the internal drainage and the substructure for the timber frame to sit on.
 
 
Grouting of floor and construction of substructure.

 
The erection of the scaffolding has begun, ready for the timber frame .



 
The site has been stoned up ready for the arrival of the timber frame and future works.


The scaffolding of the bungalow will commence next week.

 
If you haven't already heard we are holding a Community Liaison Open Evening on Thursday 3rd October at Barnabas C of E Church on Westbury Crescent.
 
It will run from 4-6.30pm, with Q&A time at 5 & 6pm, refreshments provided.
 
We look forward to seeing you there and answering any questions/ suggestions you may have?

Progress Update

Progress Report Week 6.
 
Week 6 has seen the return of the ground workers and we have started to backfill around the buildings ready for the installation of the floors.
 
 
The installation of the floors on the apartments has begun, this will be followed by the internal drainage and ductwork for services.
 

 
The substructure of the lift shaft is complete and the works for the timber frame sole plate have begun.
 
 
The drainage and floors are now being installed on the bungalows.