Progress Report Week 3.
During this week the piling works have continued without any issues and there has been no significant movement on the railway lines.
The piles on the bungalow are complete and the beam installation team have arrived on site.
Video of installation of piles.
The piling rig has now completed all of its work and has left site. Thankfully we have had no complaints about noise or vibrations during this period.