Progress Report Week 4.
 
During week 4 the piles have been cropped to the correct levels and the installation of the pile caps has commenced along with reinforced concrete beams.
 
Piles cropped.
 

Pile caps fitted.



 
Reinforced concrete beams installed.
 
 
 